The competition

4.2  A review of the NDA's invoices shows it spent £3.2 million on fees and external charges during the competition process (Figure 16). Of this amount, £3.0 million (94%) was paid to solicitors who advised on the design and running of the competition. The rest of the fees were for commercial advice services and procuring specialist software. The NDA has estimated that, during the competition, its total in-house staff costs were £5.7 million (Figure 17).

Figure 16

Fees paid by NDA to third parties

 

£000

 

Legal advice on preparing and running the competition

3,019

 

Commercial advice on the competition

128

 

AWARD software

67

 

Total fees for competition

3, 214

 

Litigation for Energy Solutions claim

8,173

 

Litigation for Bechtel claim

220

 

General management of litigation

157

 

Total fees for litigation

8,550

 

Legal advice on reaching settlement

1,154

 

Total fees for settlement

1,154

 

Financial advice on consolidation

160

 

Assurance of consolidation

154

 

Total fees for consolidation

314

 

Legal advice on termination

500

 

Other advice on termination

55

 

Total fees for termination

555

 

Total fees paid to third parties

13,786

 

Note

1  Figures may not sum due to rounding.

Source: Nuclear Decommissioning Authority invoices