2.12 Although Aspire has a very broad scope, around 85 per cent of spend was on projects and four main services (Figure 6).
2.13 Excluding projects, HMRC has spent £5 billion on maintaining and running technology services and managing the contract. HMRC monitors this cost, recording costs by service and by each major supplier for each year of the contract. These costs are consolidated with other information to produce an annual 'key messages' document which is used to review cost performance. Part Three discusses HMRC's response when actual service costs substantially vary from expected service costs.
Figure 6 Eighty-five per cent of HMRC's spend under Aspire was on development projects and the four largest services | ||||||
| Total spend | Average | Percentage | |||
Projects |
|
|
|
|
|
|
Design, build and test of new software. Integrate new software and hardware into the existing HMRC estate. Large-scale moves and changes within the estate | 2,954.3 |
| 303.0 |
| 37 |
|
Four main services |
|
|
|
|
|
|
Data Centres |
|
|
|
|
|
|
Desktop support |
|
|
|
|
|
|
Application support |
|
|
|
|
|
|
Management of the agreement |
|
|
|
|
|
|
Subtotal | 6,730.8 |
| 690.3 |
| 85 |
|
Other Services |
|
|
|
|
|
|
Telephones |
|
|
|
|
|
|
Networks |
|
|
|
|
|
|
Large-scale printing and distribution |
|
|
|
|
|
|
Automated data capture |
|
|
|
|
|
|
Other |
|
|
|
|
|
|
Total | 7,922.2 |
| 812.5 |
| 100 |
|
Notes 1 Amounts have been adjusted to 2013-14 values using the GDP deflator. 2 Numbers may not add due to rounding. Source: National Audit Office analysis of data provided by suppliers to HM Revenue & Customs | ||||||
2.14 HMRC has spent nearly £3 billion on projects (Figure 6):
• About 50 per cent has been on major change projects to develop and integrate new pieces of software and capability in its systems. These major change projects are subject to highly structured and formal governance processes.
• About 25 per cent has been on minor change projects to enhance existing software. These typically have a budget of less than £250,000 and may be a response to changes announced by ministers, or simply required to keep systems working well. They are governed by an annual bidding and prioritisation process.
• The remaining 25 per cent is on a range of other services including integration and testing done outside a major project (10 per cent), a standing charge agreed in 2009 (3 per cent) and occasional consultancy work to help business units within HMRC consider future ICT development.
2.15 After a project budget has been approved, HMRC frequently changes individual budgets through an extensive governance process. HMRC manages its annual project budget as a whole, responding tactically to any potential overspending by re-prioritising, cancelling or de-scoping projects. However, HMRC does not analyse, on a supplier basis, how agreed budgets have changed. This makes it difficult to hold the Aspire suppliers to account for their performance across the portfolio of projects.
2.16 HMRC has been unable to robustly match budgeted and actual spend across a sample of projects due to data limitations. However, we found that since April 2006 additional spend beyond the original budget had been agreed in at least 22 out of 33 projects we examined.