Overall progress on the site

2.2 The Authority aims to clear the Sellafield site by 2120. This requires completion of:

• fuel reprocessing operations on the site;

• retrieval and packaging of waste from existing storage facilities;

• transfer of waste to the Low Level Waste Repository and the proposed geological disposal facility;

• vitrification of high-level radioactive waste;6

• transfer of high and intermediate level waste into safe containers and storage; and

• final site clearance.

The Authority's detailed work schedule for the site provides for decommissioning and clean-up work to be complete by 2135 but the Authorityexpects to be able to complete decommissioning by 2120.