16th June 2016

5.14.86  On 16th June 2016, it was reported that significant progress had been made and there was now greater clarity on the position in relation to the programme for the Phase 1 schools.

5.14.87  The situation was reported as follows:

•  Broomhouse/St Joseph's Primary Schools would reopen on Monday 20th June 2016 (Subsequently achieved).

•  Pirniehall/St. David's Primary Schools would reopen on Monday 20th June 2016 (Subsequently achieved).

•  The gymnasium at Howdenhall would be available for reuse by 23rd June 2016 (Subsequently achieved).

•  Rowanfield Special School would reopen on 27th June 2016 (subsequently reopened on 24th June 2016).

•  The required information dossiers on assurances were being received by Scott Bennett for processing and approval prior to the reopening of the schools.