5.14.86 On 16th June 2016, it was reported that significant progress had been made and there was now greater clarity on the position in relation to the programme for the Phase 1 schools.
5.14.87 The situation was reported as follows:
• Broomhouse/St Joseph's Primary Schools would reopen on Monday 20th June 2016 (Subsequently achieved).
• Pirniehall/St. David's Primary Schools would reopen on Monday 20th June 2016 (Subsequently achieved).
• The gymnasium at Howdenhall would be available for reuse by 23rd June 2016 (Subsequently achieved).
• Rowanfield Special School would reopen on 27th June 2016 (subsequently reopened on 24th June 2016).
• The required information dossiers on assurances were being received by Scott Bennett for processing and approval prior to the reopening of the schools.