21st June 2016

5.14.88  An update on progress on 21st June 2016 showed that:

•  Forthview Primary School was undergoing minor adjustments to the steelwork, however it was hoped to be complete by 26th June 2016 (Subsequently delayed until 30th June 2016 due to the steelwork issue);

•  Craigour Park Primary School was expected to be complete by the end of June;

•  Craigroyston Primary School was expected to be complete in mid-July;

•  Craigmount High School was on target for completion on 6th July 2016 (Subsequently delayed until 11th July 2016);

•  Goodtrees Community Centre would reopen on 8th July;

•  Castleview Primary School was expected to be complete by mid-July;

•  Drummond High School was in the process of having significant steelwork installed in but it was still on schedule to complete by the end of July;

•  Gracemount High School was due to complete by the end of July; and

•  The Royal High School was also due to complete by the end of July.