5.14.89 The final remedial works and documentation were in fact completed for the final school, the Royal High School, on 11th Aug 2016 thus enabling the reopening of all the PPP1 schools for the return of the pupils after the summer holidays on 17th August.
5.14.90 The following is a consolidated list of the dates on which each of the PPP1 schools were handed back to the council with all works and documentation satisfactorily completed.
School | Hand back date |
Braidburn School Oxgangs Primary School St Peters RC Primary School | 20 May 2016 |
Firrhill High School | 2 June 2016 |
Pirniehall and St David's Primary Schools Broomhouse and St Joseph's Primary Schools | 15 June 2016 |
Rowanfield School Howdenhall Centre | 22 June 2016 |
Forthview Primary School | 29 June 2016 |
Goodtrees Neighbourhood Centre | 8 July 2016 |
Craigour Park Primary School Castleview Primary School | 20 July 2016 |
Craigroyston Primary School | 22 July 2016 |
Craigmount High School | 27 July 2016 |
Gracemount High School | 5 August 2016 |
Drummond Community HS | 10 August 2016 |
Royal High School | 11 August 2016 |