August 2016

5.14.89  The final remedial works and documentation were in fact completed for the final school, the Royal High School, on 11th Aug 2016 thus enabling the reopening of all the PPP1 schools for the return of the pupils after the summer holidays on 17th August.

5.14.90  The following is a consolidated list of the dates on which each of the PPP1 schools were handed back to the council with all works and documentation satisfactorily completed.

School

Hand back date

Braidburn School

Oxgangs Primary School

St Peters RC Primary School

20 May 2016

Firrhill High School

2 June 2016

Pirniehall and St David's Primary Schools

Broomhouse and St Joseph's Primary Schools

15 June 2016

Rowanfield School

Howdenhall Centre

22 June 2016

Forthview Primary School

29 June 2016

Goodtrees Neighbourhood Centre

8 July 2016

Craigour Park Primary School

Castleview Primary School

20 July 2016

Craigroyston Primary School

22 July 2016

Craigmount High School

27 July 2016

Gracemount High School

5 August 2016

Drummond Community HS

10 August 2016

Royal High School

11 August 2016