PFI/PPP contract terminations usually occur as a result of poor performance by contractors. The reasons underpinning the terminated contracts in Table 11, Appendix B, were:
Poor performance | 6 |
ICT problems, cost overruns and delays | 3 |
Failed to obtain planning permission | 2 |
Poor demand forecasting | 1 |
Construction flaws | 2 |
Technical flaws | 3 |
Reduce cost of financing | 3 |
Total | 20 |