Part 7 Abandoned PFI/PPP projects

Many PFI projects have been abandoned at the planning stage, which included some large projects such as the Paddington Basin Health Campus (2005), the University Hospitals of Leicester NHS Trust (2007) and the Colchester General Hospital (2006). These projects wrote off £14.9m, £23.m and £7.3m respectively in wasted planning, procurement and consultancy costs. PFI/PPP projects have been defined as 'abandoned' to avoid confusion with the World Bank's use of the term 'cancellation' for terminated PPP contracts.

Another example was the £1bn Armoured Vehicle Training Service project (2005). The Ministry of Defence paid £10.6m to bidders and £5.0m to consultants in the bid evaluation stage. However, it had no record of the expenditure on consultants in the earlier stages of the projects "…as records were not retained. The Department's own internal cost of resourcing this major procurement over the six years of the project was not recorded, as this was not a requirement" (National Audit Office, 2008). This reflects an appalling attitude and lax public management that is not unique to the MoD. It fails to treat staff time and resources as an opportunity cost as resources could have been used to develop another public service project or implement service improvements.

Table 9 excludes many PFI projects that were cancelled by the UK government in 2009/10 as part of austerity measures in response to the global financial crisis, for example, several Building Schools for the Future projects were cancelled or put on hold in July 2010.

The sixteen projects in Table 9 are a sample of 'abandoned' projects.

Table 9: Abandoned PFI/PPP projects in the UK

Year

Department or Authority

Project

Reason for Cancellation

Cancellation cost (£m)

2003

East Kent Hospitals NHS Trust

East Kent Hospital

£250m capital cost, cancelled after 2 years (DoH evidence to PAC 2007)

0.4

2004

Bradford Teaching Hospitals NHS Foundation Trust

Bradford Hospital

£116m project cancelled after 3 years work. (DoH evidence to PAC 2007)

0.7

March 2004

London Borough of Camden

 

Maiden Lane estate

Tenants vote by large majority to reject PFI (Hodkinson, 2011)

0.3 estimate

September 2004

Ministry of Defence

Airfield Support Services PFI Project

Contract notice Sept. 2001 for £1.5bn project but cancelled 3.5 years later (NAO, 2008)

1.0 estimate

May 2005

Royal Brompton and Harefield NHS Trust, St Mary's NHS Trust, Imperial College and Partnerships UK

Paddington Health Campus, London

Capital costs soared from £300m (OBC, 2000) to £894m and extra 7 years to complete. Cancelled on grounds of affordability, land and strategic issues (NAO, 2006)

14.9

June 2005

Ministry of Defence

Armoured Vehicle Training Service

Contract Notice October 1999, preferred bidder appointed June 2004, but failure to reach agreement (NAO, 2008)

18.5 excludes six years of internal costs & consultants costs prior to 2000

June 2005

Plymouth Hospitals NHS Trust

Derriford PFI Hospital

£300m project but 2 of 3 bidders withdrew. Cancelled on grounds of value for money risk and precedent of 1 bidder (PPP Bulletin, 11/09/09)

1.0 estimate

November 2006

Ministry of Defence

Combined Aerial Target Service (CATS)

3 bidders shortlisted September 2001, QinetiQ, privatised unit of Defence Evaluation & Research Agency in 2003 was one of bidders and launched its bid in 2003, appointed preferred bidder in March 2006 & awarded £365m contract December 2006. PFI replaced by 'contractor owned and operated service' in 2005-06 (NAO, 2007b, PAC, 2008 & Defence Industry Daily (2008).

5.0 estimate

November 2005

Whipps Cross NHS Trust

Whipps Cross Hospital PFI

£350m redevelopment, Balfour Beatty consortia withdrew leaving one bidder (PPP Bulletin 10/09/07)

3.5 estimate

June 2006

Essex Rivers NHS Trust

Colchester General Hospital

£186m capital cost project in procurement after VfM review (DoH evidence to PAC 2007).

7.3 included compensation to Amec plc led consortia

2007

University Hospitals of Leicester NHS Trust

Leicester Hospital

Preferred bidder appointed 2004 but costs rose by £210m to £921m (Building, 20/07/07)

23.4

2007

Scottish Executive

Low Moss Prison, Bishopbriggs, near Glasgow

PFI project cancelled and new public 700-cell prison operated by Scottish Prison Service. (Financial Times, 24/08/2007)

0.2 estimate

2009

Kent County Council

Medway DC Extra Care PFI via LIFT

Agreed to participate in November 2004 but later withdrew because of affordability issues (PPP Bulletin, 2008)

0.2 estimate

2007

Wiltshire Primary Care Trust

£85m LIFT project

Cancelled after three bidders shortlisted on value for money grounds (Wiltshire Council, South Wiltshire Core Strategy, 2009)

0.5 estimate

October 2010

Ministry of Defence

Defence Training Rationalisation project

Metrix Consortium appointed preferred bidder January 2007 for £14bn project, cancelled as bidder unable to deliver affordable proposal (MoD, 2010; PAC, 2010)

32.4

December 2013

Bradford City Council and Calderdale MBC

Bowling Back Lane Energy from Waste Incinerator - capital cost £181m

Govt withdrew £62.1m funding after FCC Environment & Skanska appointed preferred bidders. Councils launched Judicial Review but Govt eventually agreed settlement (Letsrecycle.com, 2014)

Settlement not disclosed 5.0 estimate

Total 16

 

 

 

114.3