(a) The Government shall be under no obligation to receive, consider, review or accept the Concept Note and/or the Unsolicited Proposal.
(b) The Government may decide not to process for approval a Concept Note and/or Unsolicited Proposal, but shall not be limited from using the asset that is the subject of the Concept Note and/or Unsolicited Proposal for the delivery of any PPP or conventional Government Project. Further, in the event that the Concept Note and/or Unsolicited Proposal is not accepted, the same Project concept may be applied by the Applicable Line Ministry and/or the Contracting Authority for the delivery of any PPP or conventional Government Project, where 24 (twenty four) months have elapsed from the date of rejection of the Concept Note and/or Unsolicited Proposal.