(a) Subject to the provision set out below, under the bonus system, the Evaluation Committee shall evaluate all the Proposals or Bids (as applicable) received in line with the provisions set out under the PPP Act and the RFP or IFB document, as applicable.
(b) When aggregating the evaluation score for the Proposal or Bid submitted by the Unsolicited Bidder, the Evaluation Committee shall include a bonus for the Unsolicited Bidder in order to enhance the evaluation score of the Unsolicited Bidder. The bonus for the Unsolicited Bidder shall be equivalent to 7% of the evaluation score assessed by the Evaluation Committee for the Proposal or Bid submitted by the Unsolicited Bidder.
(c) After taking into account the benefit of the bonus attributed to the Unsolicited Bidder, the Shortlisted Bidder or Bidder (as applicable) with the highest evaluated score will be recommended by the Evaluation Committee for selection as the Preferred Bidder.