| Project Name | Agency | Sector | Cost (Rs. Mn.) | Structure | Tender | Reason for abandonment |
| Andhra Pradesh |
|
|
|
|
|
|
| Development of Special Transport Corridor | APIIC | Roads | Not available | BOT | Not Applicable | The project is connected with SEZ development and will take off only after SEZ development |
| Sewage , Urban Road Management, Water Supply Management | Visakhapatnam Municipal Corporation | Urban Infrastructure | Not available | BOT | Not Applicable | Change in the Commissioner (the lead implementing position) |
| Krishna Water Supply Project | HMWSSB | Urban Infrastructure | 8,200 | Not Applicable | Domestic | Private operator offered much higher price (Rs42/k. litre) while the price of HMWSSB was about Rs. 3/ k. litre domestic and about Rs. 10/ k.litre for industrial customer at that time |
| Gujarat |
|
|
|
|
|
|
| Maroli Port | GMB | Ports | 10378 | BOOT | ICB | LOI has been forfeitted. The port has been put up for rebidding and EOI has been invited. Local agitations be fishermen created problems for the project |
| Dholera Port | GMB | Ports | 7500 | BOOT | Not Applicable | No good offers received in 2004 |
| Simar | GMB | Ports | 20720 | BOOT | ICB | No good offers received in 2004 |
| Mithivirdi | GMB | Ports | 5034 | BOOT | ICB | No good offers received in 2004 |
| Vansiborsi | GMB | Ports | 2749 | BOOT | ICB | No good offers received in 2004 |
| Bedi | GMB | Ports | 29050 | BOOT | ICB | No good offers received in 2004 |
| Jamnagar - Vadinar Road | GSRDC | Roads | 2200 | BOOT | Domestic | None submitted bid. Due to RPPL deciding to transport using pipelines, the liquid cargo traffic was gone. Along with economic recession, this proved disadvantageous to the project. |
| Bharuch - Dahej Road | GSRDC | Roads | 2400 | BOT | Domestic | Private developers found it non profitable |
| Savli ROB | GSRDC | Roads | 130 | BOT | Domestic | Concession period quoted in the range of 21.5 years to 23 years, which was found to be too high. Therefore, bidding cancelled and project development to be explored again when traffic level goes up. |
| Karnataka |
|
|
|
|
|
|
| Elevated Light Rail Transit System | BMRTL | Urban Infrastructure | 25,000 | BOOT | ICB | Project not functional - UB Transit Systems Team has been asked to opt for VRA |
| Punjab |
|
|
|
|
|
|
| Privatisation of Superrspeciality facilities in Amritsar and Bhatinda | Executing Government Agency | Health | Not available | BOT | ICB | Lack of political support and agitation from the public led to withdrawal of two bidders. |
| West Bengal |
|
|
|
|
|
|
| Vivekanand Flyover Project | Department of Transport, Govt. of West Bengal | Roads | 650 | BOT | Domestic | Problem in evacuating the land below the flyover which in the concession agreement was to be given to the operator for development |