| VII. OTHER CONTRACTUAL ISSUES | Yes/No | Comments |
| 64. Does the contract include a dispute resolution mechanism? | ||
| 65. If yes, does the procedure involve different stages for resolving disputes? | ||
| 66. Does the dispute resolution mechanism envisage appointing of PPP experts or arbiter among distinguished professionals? | ||
| 67. Are there strict deadlines specified for the PPP experts/arbiter to make decisions and reach resolution? | ||
| 68. Are the decisions made by experts/arbiter enforceable? | ||
| 69. Does the contract include provisions allowing the public-sector party to step-in? | ||
| 70. Doest the contract specify the circumstances under which the public-sector party is entitled to step-in? | ||
| 71. Does the contract specify who should bear the costs arising from the public sector's step-in actions? | ||
| 72. Does the contract include provisions allowing the lenders of the project to step-in? | ||
| 73. Doest the contract specify the circumstances under which the lenders are entitled to step-in? | ||
| 74. Does the contract include early termination clauses? | ||
| 75. Does the contract specify the circumstances under which the private-sector party has the right to terminate the contract before the contract expires because of a public-sector party default? | ||
| 76. Does the contract specify the circumstances under which the public-sector party has the right to terminate the contract before the contract expires because of a private-sector party default? | ||
| 77. Does the contract specify the circumstances under which the public-sector party has the right to voluntarily terminate the contract? | ||
| 78. Does the contract specify the compensation payable to the private-sector party in the above cases? | ||
| 79. Does the contract include provisions for early contract termination because of force majeure events? | ||
| 80. Does the contract specify these force majeure events? | ||
| 81. Does the contract consider corrupt gifts and fraud as causes for early contract termination? |