Preparation of PPPs

Thematic Area

What is measured

How it is scored

Preparation of PPPs

The Ministry of Finance or Central Budgetary Authority approves the PPP project before launching the procurement process.

A score of 1 if yes based on a regulatory provision. 

A score of 0.5 if yes based on a recognized practice.

 

A second approval by the Ministry of Finance or Central Budgetary Authority is required before signing the PPP contract.

A score of 1 if yes based on a regulatory provision. 

A score of 0.5 if yes based on a recognized practice.

 

Prioritization of PPP projects with all other public investment projects (e.g. in the context of a national public investment system).

A score of 1 if yes based on a regulatory provision. 

A score of 0.5 if yes based on a recognized practice.

 

Procedure to ensure consistency of PPPs with other public investment priorities.

A score of 1 if specific procedures are detailed in the regulatory framework.

A score of 0.5 if consistency is required only as a general principle.

 

Socio-economic analysis (cost-benefit analysis of the socio-economic impact of the project).

A score of 1 if required and a specific methodology developed.

A score of 0.5 if required but no specific methodology developed.

A score of 0.25 if conducted according to a recognized practice but without a specific methodology enacted.

 

Affordability assessment, including the identification of the required long term public commitments (explicit and implicit).

A score of 1 if required and a specific methodology developed

A score of 0.5 if required but no specific methodology developed.

A score of 0.25 if conducted according to a recognized practice but without a specific methodology enacted.

 

Risk identification, allocation and assessment (risk matrix).

A score of 1 if required and a specific methodology developed.

A score of 0.5 if required but no specific methodology developed.

A score of 0.25 if conducted according to a recognized practice but without a specific methodology enacted.

 

Financial viability or bankability assessment.

A score of 1 if required and a specific methodology developed.

A score of 0.5 if required but no specific methodology developed.

A score of 0.25 if conducted according to a recognized practice but without a specific methodology enacted.

 

Comparative assessment to evaluate whether PPP is the best option as compared with other procurement strategies.

A score of 1 if required and a specific methodology developed.

A score of 0.5 if required but no specific methodology developed.

A score of 0.25 if conducted according to a recognized practice but without a specific methodology enacted.

 

Market assessment (showing evidence of enough interest on the market for the project).

A score of 1 if required and a specific methodology developed.

A score of 0.5 if required but no specific methodology developed.

A score of 0.25 if conducted according to a recognized practice but without a specific methodology enacted.

 

Draft PPP contract included in the request for proposals.

A score of 1 if yes based on a regulatory provision. 

A score of 0.5 if yes based on a recognized practice.

 

Standardized PPP model contracts and/or transaction documents developed.

A score of 1 if yes based on a regulatory provision. 

A score of 0.5 if yes based on a recognized practice.