4.3  Steering Committees and Advisory Boards

In NSW, the composition of the Project Steering Committee or Project Advisory Board for a PPP project will typically include: the Responsible Agency (usually as chair), other directly affected agencies, an experienced officer from NSW Treasury and appropriately experienced representatives from other agencies or independent advisers as determined by the Responsible Agency, in consultation with NSW Treasury, or as directed by Cabinet.

The Project Director will attend all meetings and be responsible for producing the Agenda, Minutes and papers.