3.3.1  Gateway Reviews and Health Checks

The IIAF Gateway Review process provides for a series of short, focused, independent expert reviews, held at key decision points in a project's lifecycle (as depicted in Figure 3). The Gateway Reviews are appraisals of infrastructure projects, that highlight risks and issues, which if not addressed may threaten successful delivery.

The Gateway Review process is in place to strengthen governance and assurance practices and to assist delivery agencies to successfully deliver major projects and programs. Gateway Reviews are part of an assurance process which provides confidence to Government in the information supporting their investment decisions; the strategic options under consideration; and the delivery agency's capability and capacity to manage and deliver the project.

Gateway Reviews are supported by periodic Health Checks which assist in identifying issues which may emerge between decision points. Health Checks will be carried out, when required, by an independent team of experienced practitioners (industry experts including from the private sector), appointed by Infrastructure NSW.

The risk-based application of Gateway Reviews and Health Checks by Infrastructure NSW are depicted in Table 5 and Table 6.

Delivery agencies can nominate additional Gateway Reviews and Health Checks beyond those mandated by the IIAF.

Table 5  Application of Gateway Reviews by Infrastructure NSW

GATE

Tier 1 - HPHR

Tier 2

Tier 3

Tier 4

GATEWAY REVIEWS

Gateway Reviews are mandatory at all Gates.

Gateway Reviews are mandatory for Gate 0, Gate 1, and Gate 2.

Gateway Review is mandatory for Gate 0.

Gateway Reviews not required. Delivery agency assurance requirements to meet internal governance arrangements only apply.

Gate 0 Project Justification

Mandatory

Mandatory

Mandatory

 

Gate 1 Strategic Assessment

Mandatory

Mandatory

Optional

 

Gate 2 Business Case

Mandatory

Mandatory

Optional

 

Gate 3 Pre-tender

Mandatory

Optional

Optional

Not required

Gate 4 Tender Evaluation

Mandatory

Optional

Optional

 

Gate 5 Pre-commissioning

Mandatory

Optional

Optional

 

Gate 6 Post-implementation

Mandatory

Optional

Optional

 

Table 6  Application of Health Checks by Infrastructure NSW

PHASE

Tier 1 - HPHR

Tier 2

Tier 3

Tier 4

HEALTH CHECKS

Health Checks and Deep Dive Reviews27 as required by Infrastructure NSW.

Health Checks as required by Infrastructure NSW.

Health Checks as required by Infrastructure NSW.

Health Checks not required

Pre-investment decision
(Needs confirmation, Needs analysis and Investment decision)

Optional

Optional

Optional

 

Procurement

Optional

Optional

Optional

Not required

Delivery

Mandatory28

Optional

Optional

 

Post commissioning29
(Operate, Benefits realisation)

Optional

Optional

Optional

 




__________________________________________________________________________________________

27  Deep Dive Reviews are similar to a Health Check but focus on a particular issue or limited terms of reference rather than the full range of issues normally considered at a Health Check

28  Health Checks for Tier 1 - High Profile/High Risk projects are manadotry during delivery phase if this phase exceeds 6 months.

29  Health Checks may be called for Post Commissioning in an instance where Commissioning of a project/program is undertaken over a longer than usual time duration.

More Information