Confirmation of clearance of Gate

Infrastructure NSW will provide a confirmation of clearance that a project can move to the next Gate or Health Check. This clearance reflects that a delivery agency has completed a Gateway Review for a particular stage of the project and an appropriate Close-out Plan is in place to assist with project development or delivery. The clearance is not a Gateway Review approval or an endorsement of the project.

Table 7  Reporting/presentation of Gateway Review and Health check findings to Cabinet33

GATE/PHASE

Tier 1 - HPHR

Tier 2

Tier 3

Tier 4

GATEWAY REVIEWS

 

 

 

 

Gate 0 Project Justification

Reported by exception

Reported by exception

Reported by exception

Not applicable

Gate 1 Strategic Assessment

Routinely reported and presentation by CEO Infrastructure NSW

Routinely reported where applicable34

Routinely reported where applicable34

Gate 2 Business Case

Gate 3 Pre-tender

Gate 4 Tender Evaluation

Gate 5 Pre-commissioning

Gate 6 Post-implementation

HEALTH CHECKS

 

 

 

 

Pre-investment decision (Needs confirmation, Needs analysis and Investment decision)

Routinely reported and optional presentation by CEO Infrastructure NSW

Routinely reported where applicable34

Routinely reported where applicable34

Not Applicable

Procurement

Delivery

Routinely reported and presentation by CEO Infrastructure NSW

Post commissioning35 (Operate, Benefits realisation)

Routinely reported and optional presentation by CEO Infrastructure NSW




_________________________________________________________________________________________________

33  For Projects NSW projects presentations are made by the Secretary or Chief Executive of the nominated GCA

34  Routine reporting includes noting that a Review was undertaken, where relevant a summary of outcomes may be provided and/or a presentation may be made by the CEO Infrastructure NSW.

35  Health Checks may be called for Post Commissioning in an instance where Commissioning of a project/program is undertaken over a longer than usual time duration.