Table D1 Regular project reporting - Overall project status definitions

Status

 

Legend on HPHR report

Detailed description in portal

Green

No major unmitigated risks

No major unmitigated risks identified

Amber

Major risks appropriately mitigated

Major risks identified but appropriate mitigating actions being taken

Red

Further action required to mitigate major risks

Major unmitigated risks identified - further action required

The definitions for the traffic light system for project time and cost status are shown in Table D2 and Table D3.