Table D2 Regular project reporting - Project time status definitions

Status

 

Legend on HPHR report

Detailed description in portal

Green

On-track

Project/program is on track and is expected to be delivered within approved timeframes. No major unmitigated risks identified.

Amber

At risk

Project/program is at risk of not being delivered within approved timeframes. Appropriate mitigating actions are being taken that address major risks to time.

Red

Not on-track

Project/program is not on-track and is not expected to be delivered within approved timeframes. Further actions are required to address unmitigated major risks to time.