◼ provide an outline of a project plan that includes the major project components for implementing the project or program from resource allocation decision to operation, (that is, procurement, design/development/construction, commissioning, and operation)
◼ outline the major requirements to support these project components including key milestones and delivery dates, major decision points, critical path items, key dependencies, resourcing requirements and strategy, risk management plan, governance arrangements, environmental planning requirements, change management and stakeholder consultation requirements
◼ Note, the project plan should not be a high level work plan of the project phases and should provide the due dates for the major project deliverables/milestones
◼ A Gantt chart is preferable: the level of detail should be appropriate for an executive audience and enable an expert assessment of the soundness of the proposed workplan