Project planning (Section 5.5) - What is the process for identifying, monitoring and managing risk during the implementation of the project?

Document the risk analysis by:

stating what the project risk is assessed as (Gateway Project Profile Assessment risk evaluation tool)

identifying the range of significant risks

measuring each of the risk exposures in the project/program, in terms their likelihood (e.g. almost certain, unlikely) and their consequences (e.g. very high, moderate)

Risk exposure = Consequences x Likelihood

Likelihood

Consequences

Rare -1

Unlikely -2

Moderate -3

Likely -4

Almost certain - 5

Very high - 5

5

10

15

20

25

Major - 4

4

8

12

16

20

Moderate - 3

3

6

9

12

15

Minor - 2

2

4

6

8

10

Insignificant -1

1

2

3

4

5

Key

Risk Exposure:

Very high

High

Moderate

Low

assessing whether the level of each risk is acceptable, and what the controls are to mitigate or reduce the level of gross risk

Document risk management approach by:

selecting the option most appropriate to mitigate or reduce each identified risk

identifying and assigning the resources necessary to do the work

stating what will be done to monitor the status of each risk, and checking controls are performed and are effective