The Reporting phase will comprise the following activities:
• Draft the country case studies, sector review notes, ISP review notes, Portfolio analysis, and evaluation synthesis report;
• Submit workshop presentation reports including the institutional benchmarking across the selected MDBs and make any required adjustments/ revisions based on comments from the Task Manager and IDEV Management, as well as relevant departments within the Bank;
• Submit Draft reports for selected case studies and make any adjustments/revisions based on comments from the Task Manager and IDEV Management, the Reference Group, internal and external peer reviewers;
• Submit the Final Evaluation Reports;
• Make presentations as required by IDEV Task Manager/ Management;
• Submit Draft Evaluation Reports and make any required adjustments/revisions based on comments from the Task Manager, and IDEV Management, as well as relevant departments within the Bank.
The Evaluation Outputs are the following:
1. A Portfolio Review Report
2. A Policy Review Report
3. Twenty (20) Project Results Assessments
4. Non-lending interventions Review Note
5. PPP Institutional Arrangements in MDBs (Benchmarking Exercise Note)
6. Nine (9) Country Case Studies
7. Three (3) Sector Synthesis Notes (Power, Renewable Energy, Transport)
8. The Evaluation Report
Proposed outlines for these Outputs are presented in Annex 8 to 14 of the Volume 2 of the Inception Report (Technical Annexes).
The following graph shows the integration and interdependence between the evaluation components/Outputs:
Figure 8 - Integration and Interdependence of the Evaluation Components/Outputs
|
Source: IDEV |