3.1.4  Change in law and related Project Agreements

As with other provisions in the PPP Contract, the treatment of change in law under the Project Agreements should ensure the Private Partner is not obliged to give its sub-contractors more protection than the Private Partner is entitled to under the PPP ContractSee Sections 1.1.4, Force Majeure and 2.1.4, Material Adverse Government Action.