As with other provisions in the PPP Contract, the treatment of change in law under the Project Agreements should ensure the Private Partner is not obliged to give its sub-contractors more protection than the Private Partner is entitled to under the PPP Contract. See Sections 1.1.4, Force Majeure and 2.1.4, Material Adverse Government Action.