(5) If a Change in Law: (a) results in the Private Partner not being able to achieve the [insert defined term for services commencement date] within [•] months after the [insert defined term for scheduled services commencement date]; or (b) prevents a Party from performing its material obligations under this PPP Contract for a period of [•] consecutive days; or (c) results in performance of the PPP Contract being illegal and such illegality cannot be remedied by a Contracting Authority variation, either Party may in its discretion terminate this PPP Contract by issuing a written termination notice which shall take effect [thirty (30) calendar] days after receipt of such termination notice. If, at the end of this [thirty (30)] day period, the Change in Law continues, the PPP Contract shall be terminated pursuant to clause [insert reference to the clause governing termination] and the Private Partner shall be entitled to the compensation set out under clause [insert reference to Change in Law termination payments clause]. |
|