Compensation on Force Majeure Termination

(3)  If this PPP Contract is terminated for Force Majeure in accordance with Clause [ ], the Contracting Authority shall pay the Private Partner an amount equal to the sum of:

(a)  Outstanding Senior Debt, if any; plus

(b)  Initial Equity and any outstanding principal under the Subordinated Finance Documents as at the Termination Date [less any Distributions or subordinated debt interest payments already made]; plus

(c)  redundancy payments for employees of the Private Partner that have been or will be reasonably incurred by the Private Partner as a direct result of termination of this PPP Contract, plus

(d)  any Sub-Contractor Breakage Costs.