2.2.2.1  General principle

Clause 2.3 contains the order of precedence that will apply between the various documents comprising the Project Deed. Generally, the clause provides that the terms and conditions take precedence over the technical and functional requirements. This is because the terms and conditions give context to and inform the technical and functional requirements. In terms of the technical and functional requirements, while the PSDR will typically have its own order of precedence, the Delivery Requirements will take priority over the Project Scope.