2.7.1  General principle

It is the intention of the parties that all rights and liabilities of the parties (including the calculation of compensation) are regulated by the terms of the Project Deed, limiting the ability of Project Co to make extra-contractual claims against the State such as for negligence or misrepresentation. To give effect to this, specific provisions have been included in clause 5.6 and a detailed compensation regime is included in the Change Compensation Principles.