Principle 4

Project Co accepts all risk in connection with the PSDR and warrants that the PSDR is fit for the purpose of enabling Project Co to carry out the Project Activities and ensuring that the Works satisfy the purposes that are set out in the PSDR.

The successful Respondent has been selected in part because of its expertise in delivering the type of infrastructure the subject of the Project. Accordingly, the State expects the successful Respondent to have reviewed and vetted the technical requirements for the Project set out in the PSDR.