Project Co must coordinate the Project Activities with Authorities and anticipate, plan for and price the impact on the Project of the acts and omissions of Authorities acting in accordance with their statutory powers. To give effect to this risk allocation, clause 7.1 of the PV Standard Project Deeds includes an acknowledgement from Project Co that Authorities may exercise their statutory functions and powers in a way that disrupts, interferes with or affects the Project Activities or the Project Area. When this occurs Project Co is not entitled to relief or compensation. This is a business as usual risk and the State does not consider that Project Co should be treated any differently from the rest of the community when it comes to the exercise of an Authority's statutory powers.