The following parts of the PV Standard Project Deeds will require consideration on a project specific basis:
• the Subcontractor termination amounts payable by the State, where the State terminates the Project Deed for convenience, will be considered and confirmed on a project specific basis, including the percentage of the unpaid contract sum and whether different values should apply during the Development and Operational Phases. These amounts are to reflect actual profit as bid by the Key Subcontractors only. All payments amounts must be approved by DTF prior to Contract Close;
• identification of the Subcontracts that will fall within each of the subcontract definitions referred to in section 2.11.2;
• the value to be used to determine whether a Subcontract is a Significant Subcontract;
• clause 9.2(b)(ii) may in very limited circumstances require amendment to reach further down the subcontracting chain, depending on the subcontracting structure proposed by the Successful Respondent; and
• while the PV Standard Project Deeds include a definition for and references to a Management Services Contract and Management Services Contractor, this will only be required when a Management Services Contractor is proposed by the Successful Respondent.