Project Co is entitled to compensation and relief for a Compensable Extension Event and/or Compensable Intervening Event for Industrial Action which occurs at or in the direct vicinity of the Project Area and is the direct result of an act or omission of the State or State Associate acting in connection with the Project, other than an act or omission which:
• is permitted, authorised or required under a State Project Document or required to comply with any Law or Standard;
• is undertaken as part of any Interface Works (refer to section 2.20); or
• is contemplated by clause 7.1 where the Authority is acting in accordance with its statutory powers (see section 2.9.1 for further discussion on the operation of clause 7.1).