When a Contamination Compensation Event occurs (see Diagram 10 above):
• the Remediation will be treated as a State Initiated Modification;
• relief and compensation will be provided in accordance with Item 11, Table 1 of the Change Compensation Principles;
• during the Development Phase, this will be an Extension Event; and
• during the Operational Phase, this will not be an Intervening Event (on the basis that the State's position is that Project Co will not automatically be entitled to be relieved of its obligations to perform the Services and any specific relief will be addressed as part of the Modification process).