Project Co is required to make enquiries as to the location of existing Utility Infrastructure and must liaise with the owner of that Utility Infrastructure and the relevant Utility provider as to the need for any potential relocation, protection or decommissioning of the Utility Infrastructure. Project Co is required to obtain the State's consent to relocate Utility Infrastructure within or outside the Project Area, or to construct or modify any Utility Infrastructure outside the Project Area.
Project Co assumes the risk in relation to existing Utility Infrastructure and the continuous supply and sufficiency of Utilities in connection with the Project Activities, the need to relocate, protect or modify such Utility Infrastructure, and any access to the Site or interference with the Project Activities by or on behalf of a Utility provider (see section 2.13.7.2 for a discussion of the Utilities regime under the MTPFA).