2.25.2.2  Technical Acceptance Outstanding Items

The Independent Reviewer may determine or Project Co and the State may agree that certain Works or Development Activities which were otherwise required to be completed by Technical Acceptance can be deferred. The Independent Reviewer may only exercise this right where the Works or Development Activities are Minor Defects. Such deferred work will either need to be completed by Commercial Acceptance as Technical Acceptance Outstanding Items or by Final Acceptance as Remaining Works.

The approach to Technical Acceptance Outstanding Items is set out in Diagram 11 below.

Diagram 11