2.25.3.2  Project specific amendment

Those aspects of the Works that are required to be completed in order to achieve Technical Acceptance need to be determined on a project specific basis.

In sizing the Commissioning Period, agencies need to balance the importance of having time to ensure the Maintained Assets are running smoothly before the Operational Commencement Date with the high cost the State will pay for each day of this period given that at this point in time debt will be almost fully drawn down. Accordingly, the duration of the Commissioning Period needs to be determined on a project specific basis prior to the release of the RFP and must be agreed with DTF.

The definition of Commissioning Requirements and State Operational Commissioning needs to be completed on a project specific basis.