The following matters will be considered and completed by the State on a project specific basis:
• whether there is a requirement to ramp up Services if full Services delivery and full Service Payment will not commence from the Date of Commercial Acceptance;
• Works and Defects (other than Minor Defects) that are agreed to be Remaining Works (which must be approved by DTF);
• the time periods for notice to the State of when Project Co reasonably expects to achieve Commercial Acceptance;
• the requirements for Commercial Acceptance (which will be set out in the PSDR); and
• generally due to the legislative and contractual framework for roads projects, the Date of Commercial Acceptance must be the date of the Certificate of Commercial Acceptance, but for other Projects, the Date of Commercial Acceptance can be prior to the date of the Certificate of Commercial Acceptance.