2.25.5.1  General principle

Returned Works are those parts of the Works that have been designed or constructed by Project Co during the Development Phase which will not form part of the Maintained Assets during the Operational Phase, but will instead be progressively handed back to the relevant Returned Asset Owner prior to Returned Works Acceptance (e.g. footpaths, utility pits and conduits, water and sewerage reticulation and fly overs etc.).

The Independent Reviewer will determine (in consultation with the relevant Returned Asset Owner) whether a Returned Work has achieved Returned Works Acceptance

Returned Works are likely to achieve Returned Works Acceptance at different stages during the Development Phase in accordance with requirements set out in the PSDR