2.25.5.3  Project specific amendments

The following matters will be considered and completed by the State on a project specific basis:

•  the inclusion of a Returned Works regime, which is applicable only where it is part of Project Co's scope to undertake works and construct infrastructure which will be owned and operated by others during the Operational Phase; and

•  the timing for Returned Works Acceptance, which will depend on when the Returned Asset is required by the Returned Asset Owner and is assumed in the PV Standard Project Deeds to occur by Commercial Acceptance at the latest. If this is not the case, and certain Returned Works will be completed or accepted after Commercial Acceptance, then these Returned Works should be included in the Remaining Works Schedule for completion by Final Acceptance.