2. Project Deed guidance
>
2.26 Time, Extension Events and Compensable Extension Events (clause 26)
2.26
Time, Extension Events and Compensable Extension Events (
clause 26
)
More Information
2.26.1 General principle
2.26.2 Primary obligation (clause 26.1)
2.26.3 Development Phase Program (clause 26.2)
2.26.4 Sole remedy for late Acceptance (clause 26.3)
2.26.5 Independent Reviewer's review of progress (clause 26.4)
2.26.6 Extension of time (clauses 26.5 - 26.9)
2.26.7 Unilateral extensions (clause 26.10)
2.26.8 Entitlement to financial compensation for delay (clause 26.12)
2.26.9 Share of Prolongation Costs (clause 26.13)
2.26.10 Concurrent Delays (clause 26.14 and 35.8)
2.26.11 Acceleration (clauses 26.15 - 26.19)