2.26.3.2  Project specific amendments

Where the State requires Project Co to meet specific dates (such as Commercial Acceptance by the Date for Commercial Acceptance) these should be identified as separate milestones in the Project Deed. These milestone dates should also be extended for delays to completion of the milestones caused by Extension Events to preserve the State's ability to enforce the milestone dates, however Project Co will not be entitled to compensation for any extension to a milestone.