2.26.5.2  Project specific amendments

The following elements of the regime may be subject to project specific considerations:

•  the period of time (if any) before the Independent Reviewer can issue a notice of non-compliance (this should be determined taking into account the length of the Development Phase);

•  the frequency of the Independent Reviewer's notices of non-compliance; and

•  the maximum period of time after the Date for Commercial Acceptance within which Project Co must demonstrate that Commercial Acceptance will be achieved (see section 2.53.3 and 2.53.5 for a discussion on Cure Program and cure periods).