2.27.6  Termination for a Force Majeure Event

If a Force Majeure Event:

•  has caused Major Loss or Damage and the State directs Project Co not to repair or rebuild the Project Assets, the State must terminate the Project Deed for a Force Majeure Event as if the Major Loss or Damage was a Force Majeure Termination Event; or

•  otherwise prevents Project Co or the State from carrying out all or a material part of their respective obligations for a period exceeding 180 consecutive days, either party may exercise the right to terminate the Project Deed for a Force Majeure Termination Event.

In both termination scenarios, Project Co will be entitled to the Termination Payment in respect of a Force Majeure Termination Event. See section 3.4 for further discussion on Termination Payments.