2.53.1  Defaults (clause 45.2)

If a Project Entity breaches a State Project Document and that breach is not categorised as a Performance Failure, Major Default or Default Termination Event then the State has the right to serve a Default Notice on Project Co to cure the Default (or where it cannot be Cured, meet the State's reasonable requirements) within 20 Business Days or such longer period as the State notifies.

If the Default is not cured or, where the Default cannot be cured, the reasonable requirements of the State are not met within the notified period, the Default becomes a Major Default. This interim process gives the parties the ability to manage minor breaches that are not otherwise regulated by the State Project Documents before they are elevated to Major Defaults.