Project Co must provide a Cure Program within 10 Business Days after receiving a Major Default Notice.
Where the Major Default is a failure by Project Co to achieve Commercial Acceptance by the Date for Commercial Acceptance and Project Co has provided a Remediation Plan in accordance with the requirements of the Independent Reviewer's review of progress (in accordance with clause 26.4), Project Co may submit that Remediation Plan as the Cure Program for the Major Default.