3.2  Review Procedures (Schedule 4)

The Review Procedures will only apply to plans, reports, updated Financial Models and other documents that are subject to review in accordance with the Review Procedures, but do not apply to the Design Documentation. The Design Documentation is subject to the Design Development Process set out in the Design Appendix in the PSDR. 

The Review Procedures will set out the general basis on which all such documents can be reviewed and commented upon. If there are additional bases on which a Reviewing Party should be entitled to comment on a document, these need to be expressly included in the Review Procedures in respect of that document. For example, in relation to reviewing variations to the Financial Model as a result of a Model Variation Event, the Review Procedures must permit the State to reject a variation to the Financial Model in circumstances where the State considers (acting reasonably) that the updated Financial Model is not correct or would have unintended consequences that impact on the Project.