The purpose of the Change Compensation Principles is to set out:
• Project Co or the State's entitlement to compensation for a Change Compensation Event; and
• procedural requirements in connection with Project Co making a Claim for compensation under the Change Compensation Principles.
The Change Compensation Principles do not apply to Augmentations unless expressly stated in the Augmentation Process Schedule.