3.4.1  Grounds for termination

The State may terminate the Project Deed prior to the Final Expiry Date:

•  for a Force Majeure Termination Event, where there is a Force Majeure Termination Event (or the State directs Project Co not to repair or reinstate the Project Assets in the case of Major Loss or Damage);

•  for Convenience; or

•  if a Default Termination Event occurs.

Project Co is only entitled to terminate the Project Deed for a Force Majeure Termination Event.