(a) (Order of precedence): Subject to clause 2.3(b), the following order of precedence applies in the event of any inconsistency, ambiguity or discrepancy between the various documents comprising this Deed:
(ii) Schedules; [Note: To be determined on a project specific basis but should include Schedules 1 to 6, 10 to 16, 18, 19, 22 and 23.]
(iii) the Delivery Requirements;
(iv) the Schedules not referred to in paragraph (ii);
(v) the Project Scope; and
(vi) the Annexures (if any) other than the PSDR.
(b) (Higher or greater requirement): To the extent that any part of this Deed imposes on Project Co a higher or greater requirement, standard, quality, level of service, staffing level, quantum or scope than any other part of this Deed, unless the context otherwise expressly requires, that higher or greater requirement, standard, quality, level of service, staffing level, quantum or scope prevails.