(a) (State Approvals): The State:
(i) has obtained, or will obtain, the State Approvals on or before the dates set out in Attachment 2;
(ii) will, subject to the provision of all required information and assistance from Project Co in accordance with clause 6.1(c), ensure that Project Co has the benefit of such State Approvals as required to perform the Project Activities on and from the relevant dates set out in Attachment 2; and
(iii) will satisfy the conditions and requirements of State Approvals which are required to be satisfied or fulfilled by the State (if any) in accordance with Attachment 2.
(b) (Changes to State Approvals): The State must obtain any changes to a State Approval required as a consequence of:
(i) a State Initiated Modification;
(ii) an Extension Event; or
(iii) an Intervening Event.
(c) (Reasonable assistance): Project Co must provide to the State all reasonable assistance and all information reasonably requested by the State in order for the State to:
(i) obtain the State Approvals that have not been obtained as at the date of this Deed;
(ii) obtain any changes to a State Approval; and
(iii) without limiting clause 6.2(c) or clause 6.2(d), satisfy or fulfil the conditions and requirements of any State Approvals which are required to be satisfied or fulfilled by the State in accordance with Attachment 2.
(d) (State Approval Event): If a State Approval Event occurs:
(i) at the request of the State, Project Co must provide all reasonable assistance in connection with dealing with the State Approval Event;
(ii) Project Co acknowledges and agrees that as between the State and Project Co, the State may deal with the State Approval Event as it sees fit (including, if appropriate, conducting any legal challenge in the name of Project Co); and
(iii) the State Approval Event will be deemed to be a Modification in respect of which Project Co may submit a Modification Proposal in accordance with clause 35.2(a) and Project Co's or the State's entitlements will be determined in accordance with clause 35 and the Change Compensation Principles as if the State Approval Event was a State Initiated Modification.
(e) (Condition precedent): Project Co is not entitled to make any Claim against the State in respect of any State Approval Event (including its impact) unless it has given notice under clause 35.2(a)(ii).