(a) (Submission): Project Co must:
(i) update the Bid Project Plans in accordance with [##] of the PSDR by the "Project Plan submission date" set out in [##] of the PSDR; and
(ii) for any other Project Plan in respect of which there is no Bid Project Plan, prepare the Project Plan in accordance with [##] of the PSDR,
and submit those Project Plans to the State (and, where applicable, in accordance with [##] of the PSDR, the Independent Reviewer) for review in accordance with the Review Procedures.
(b) (Updates): Project Co must update the Project Plans in accordance with [##] of the PSDR.
(c) (Not part of this Deed): The Project Plans do not form part of this Deed. [Note: May be amended on a project specific basis. See Guidance Notes for further detail.]
(d) (Delivery): Unless otherwise agreed by the State, notwithstanding clause 17.1(c), Project Co must carry out the Project Activities in accordance with the Project Plans.
(e) (Additional information): Project Co must provide to the State and, where applicable, the Independent Reviewer, any additional information in connection with the Project Plans reasonably requested by the State and, where applicable, the Independent Reviewer.