23.  Commissioning

During the Commissioning Period, without limiting its obligations and the State's rights under clause 24, Project Co must:

(a)  (carry out all requirements): carry out all Commissioning Requirements in accordance with the Operational Readiness and Ramp-Up Plan, the Commercial Acceptance Plan and otherwise in accordance with this Deed; and

(b)  (provide State with access): without limiting clause 15.1, provide the State, the State Associates and any other person authorised by the State with access to those parts of the Site and the Works in accordance with the Site Access and Interface Protocols to enable the State and the Operator to carry out the State Operational Commissioning.